Most disputes are settled by what was written down before anyone thought there would be one.
Barrister & Co. is a firm of advocates practising from chambers on Armenian Street, George Town, four minutes on foot from the Madras High Court. It has done so since 1971. Its work is the drafting that keeps clients out of court and the litigation, arbitration and appeals that follow when drafting was not enough.1
The firm was founded in 1971 by T. S. Krishnamurthi, who had read for the Bar at Gray’s Inn and come home to practise at Madras. The name he gave it was a small joke at his own expense, since India has no barristers, and nobody since has had the heart to change it.
Ten advocates practise from chambers today: one Senior Advocate, five partners, a senior associate and three associates. Work is taken on by a partner, who remains responsible for it until it ends, and is done by the smallest team that can do it properly.
The firm appears mainly before the Madras High Court and the courts and tribunals sitting in Chennai, and travels to the Madurai Bench, the district courts of Tamil Nadu and the Supreme Court when a matter requires it. It advises in Tamil and English and drafts in English.
Practice areas
Seven areas, each set out in full at ¶ 2.1 to 2.7 on the practice page with the kind of matter the firm takes and the partner who leads it.
¶ 3 Counsel, by year of enrolment
Ten advocates. Thirty-eight years between the first call and the last.2
- 1984K. R. VenkataramanSenior Advocate, 2009
- 1996Meenakshi SundaramPartner
- 1998Lakshmi NarayananPartner
- 2001Priya ChandrasekaranPartner
- 2003S. Mohammed FaizalPartner
- 2005Arjun BalasubramanianPartner
- 2012Divya RamanathanSenior Associate
- 2017Vignesh KumaraswamyAssociate
- 2019Anitha JosephAssociate
- 2022Hariharan IyerAssociate
Madras High Court · O.S.
Reg. 4118 of 2024
¶ 4 Nine reported decisions
Matters argued by the firm that a law report has since printed, 2017 to 2024, in the order the reports carry them. Two were lost at first instance.3
- 4.1Kaveri Solar Power Ltd. v. Sundaram Infra EPC (P) Ltd.2024 SCC OnLine Mad 3118Madras High Court, Original Side, 2024Petition under s. 34 dismissed; award of ₹71.3 crore upheld
- 4.2Coimbatore Pumps & Castings Ltd. v. Anand Hydraulics(2021) 7 SCC 214Supreme Court of India, 2021Appeal dismissed; a court under s. 34 does not sit in appeal on the evidence
- 4.3Ref. under s. 34(3): Muthiah Chettiar v. Salem Steels (P) Ltd.(2019) 4 CTC 512Madras High Court, Full Bench, 2019Reference answered; limitation runs from receipt of the signed copy
- 4.4Meridian Auto Components (India) (P) Ltd. v. DCIT(2022) 196 ITD 441 (Chen.)Income Tax Appellate Tribunal, Chennai 'B' Bench, 2022Transfer-pricing adjustment of ₹27.4 crore deleted
- 4.5Amirtham Hotels (P) Ltd. v. Asst. Commissioner (ST)2023 SCC OnLine Mad 5904Madras High Court, 2023GST demand for the pre-migration period quashed
- 4.6Kanaka Durga Jewellers v. Sri Kanaka Jewellery Mart(2020) 84 PTC 219 (Mad)Madras High Court, Commercial Division, 2020Interim injunction confirmed; deceptive similarity in a Tamil word mark
- 4.7Sundararajan v. Special Tahsildar (LA), Sriperumbudur(2019) 6 MLJ 88Madras High Court, 2019Compensation enhanced to ₹41.6 lakh an acre with statutory interest
- 4.8Vedavalli Ammal v. R. Rajagopalan(2018) 5 CTC 771Madras High Court, Original Side (Testamentary), 2018Probate granted; suspicious circumstances not made out
- 4.9Nachiappan v. State of Tamil Nadu(2017) 3 MLJ 402Madras High Court, 2017Cancellation of tender set aside; matter remitted for fresh consideration
¶ 5 One matter, in the order it happened4
Kaveri Solar Power Ltd. v. Sundaram Infra EPC (P) Ltd.
Arbitration under clause 41 of an EPC contract for a 60 MW plant at Tuticorin. Chennai seat, three arbitrators.
- Claimed
- ₹118.4 crore
- Awarded
- ₹71.3 crore
- Recovered
- ₹94.7 crore
- Sittings
- 19
- Elapsed
- 5 years, 6 months
- 09.01.2019
Notice of dispute
Served under clause 41.2 for delay, disruption and eleven unpaid running account bills. Claim stated at ₹118.4 crore.
- 22.02.2019
Reply
Liability denied in full. A counter-claim for liquidated damages foreshadowed but not quantified.
- 14.03.2019
Application under s. 11
Each side had nominated an arbitrator and neither would agree on the third. The High Court was asked to appoint.
The clause gave thirty days to agree. Nobody has ever agreed in thirty days.
- 27.06.2019
Tribunal constituted
A retired judge of the Madras High Court appointed as presiding arbitrator. Seat at Chennai; proceedings under the 1996 Act.
The seat decides which court supervises. Chennai was written into clause 42. Where it is not, that is the first thing fought over.
- 30.08.2019
Statement of claim
Filed with 1,340 pages of running account bills, site instructions, hindrance registers and daily progress reports.
- 11.11.2019
Defence and counter-claim
Counter-claim quantified at ₹36.2 crore for liquidated damages and cost of rectification.
- 20.03.2020
Sittings suspended
Hearings adjourned sine die. The tribunal resumed by video from October, sitting on Saturdays.
- 04.02.2021
Section 9 application
Two performance bank guarantees of ₹14.8 crore were called. An application under s. 9 was moved in the High Court that morning and an interim order restraining encashment made the same afternoon.
A s. 9 order runs alongside the arbitration. It is the one part of an arbitration a court will still decide in a morning.
- 08.09.2022
Evidence closed
Six witnesses over nineteen sittings. Cross-examination of the employer's delay expert ran four days and turned on a single revised programme dated 11.06.2018.
- 12.12.2022
Award reserved
Written submissions of 214 pages and a joint chronology filed by consent.
- 30.05.2023
Award
₹71.3 crore with interest at 9 per cent from 01.04.2018 and costs. Counter-claim dismissed in its entirety.
- 28.08.2023
Petition under s. 34
The employer challenged the award on patent illegality and on the delay expert's evidence being disregarded.
- 19.04.2024
Challenge dismissed
Reported at 2024 SCC OnLine Mad 3118. The court held that the reappraisal asked for was an appeal by another name.
See ¶ 4.1. Reported judgments are listed there in the order the reports carry them.
- 11.07.2024
Satisfaction of the decree
₹94.7 crore received with interest. File closed and papers returned to the client.
Chambers
No. 14, Armenian Street, George Town, Chennai 600 001.5 Telephone +91 44 2522 0417. Open Monday to Saturday, 10.00 to 18.00, except court holidays.
To instruct the firm, write to chambers@barristerandco.in with a paragraph describing the matter and the court, if any, in which it stands. A partner replies within two working days to say whether the firm can act and, if it can, sends a letter of engagement setting out the fee.6
Conferences are held at chambers between 10.00 and 13.00 on days the partner concerned is not in court, and are fixed by letter or telephone. Papers may be sent ahead by post or, for anything under fifty pages, by e-mail.
- Rule 36, Section IV, Chapter II, Part VI of the Bar Council of India Rules restrains advocates from advertising or soliciting work. This site is published under the proviso to that rule and is limited to the firm's name, address, areas of practice and the particulars of its advocates.
- Every advocate named at ¶ 3 is enrolled with the Bar Council of Tamil Nadu and Puducherry. The year given is the year of enrolment; the designation of Senior Advocate is conferred by the High Court and its year is given separately.
- The judgments at ¶ 4 are reported decisions in matters in which the firm appeared for one of the parties. They are public documents and are named here as they are named in the reports. Matters that were lost are listed with the rest; a citator that prints only wins is not a citator.
- The history at ¶ 5 is set out with the client's written consent and is taken from the record. Sums are as recorded in the award and the decree. Six of the sittings were held by video between March 2020 and February 2021.
- Chambers are at No. 14, Armenian Street, George Town. The High Court's gate on N.S.C. Bose Road is about four minutes on foot; the Broadway bus terminus and the Chennai Beach suburban station are both within ten.
- Fees are settled by a letter of engagement before any work begins, on a per-appearance or per-matter basis. The firm does not publish a scale, and the first conference carries no charge if the firm decides it cannot act.